"Ruling on Dakota Access Pipeline Shutdown Months Away"

"BISMARCK, N.D. — A federal judge won’t decide until later this year whether to shut down the disputed Dakota Access oil pipeline while federal officials conduct a more thorough environmental review.

U.S. District Judge James Boasberg on Wednesday approved a schedule under which both sides in a lawsuit over the pipeline will submit written arguments on the matter in July and August.

“We would expect a decision sometime after that, probably September,” said Jan Hasselman, an attorney for the Standing Rock Sioux, which filed the lawsuit last summer that was later joined by three other Sioux tribes."

Blake Nicholson reports for the Associated Press June 22, 2017.

SEE ALSO:

"Oil To Keep Flowing In Dakota Line While Legal Battle Continues" (Reuters)

Source: AP, 06/23/2017