"EDF Raises French EPR Reactor Cost To Over $11 Billion" [1]
"French utility EDF has raised the cost of the construction of its next-generation nuclear reactor by more than 2 billion euros on Monday, the latest in a series of overruns for the first EPR reactor built in France."
"Stricter regulation in the wake of the Fukushima nuclear disaster contributed to bringing the total cost of the 1,600-MW Flamanville European pressurized reactor to 8.5 billion euros ($11.11 billion), the group said.
In 2005, the state-owned utility estimated the reactor's cost at 3.3 billion euros."
Muriel Boselli and Michel Rose report for Reuters December 4, 2012. [2]
SEE ALSO:
"Signs of Tampering Found at Shut San Onofre, California Nuclear Plant" (Reuters) [3]
"Clinton in Prague To Lobby for Westinghouse Nuclear Bid" (Reuters) [4]
"Nuclear Power Whistleblowers Charge Federal Regulators With Favoring Secrecy Over Safety" (Huffington Post) [5]
"EDF Extends Life of Two Nuclear Power Stations" (Independent) [6]