"Federal regulators have given U.S. grid companies until Jan. 1, 2028, to shield vulnerable high-voltage transformers from damaging electrical currents triggered by a massive solar eruption.

The Federal Energy Regulatory Commission unanimously issued Order 851 last Thursday, establishing a revised timetable and requirements for protecting essential and hard-to-replace grid transformers from overheating and possible irreparable damage from a once-in-a-century solar burst.

The action completes nearly all of a rulemaking FERC began in 2013, setting off a sometimes furious debate between industry experts and members of a congressional commission about the risk that a solar superstorm would wreck on scores of transformers, causing a catastrophic blackout."

Peter Behr reports for EnergyWire November 19, 2018. [2]

Disasters [3]
Energy & Fuel [4]
National (U.S.) [5]
Public [6]
Source: EnergyWire [2], 11/20/2018
  • Contact Us  |
  • Donate  |
  • Join  |
  • Members  |
  • Privacy & Security Policies  |
  • Reach SEJ Members  |
  • Renew  |
  • Site Map
The Society of Environmental Journalists
1629 K Street NW, Suite 300, Washington, DC 20006
Telephone: (202) 558-2055
Email: sej@sej.org
© 2026 The Society of Environmental Journalists. All Rights Reserved.
All graphics © SEJ, unless otherwise stated.

Source URL:https://www.sej.org/headlines/ferc-regulators-race-solar-eruption-threats-grid

Links
[1] https://www.sej.org/headlines/ferc-regulators-race-solar-eruption-threats-grid [2] https://www.eenews.net/energywire/stories/1060106561 [3] https://www.sej.org/category/topics-beat/disaster [4] https://www.sej.org/category/topics-beat/energy [5] https://www.sej.org/category/region/national [6] https://www.sej.org/taxonomy/term/81