"Santa’s elves aren’t the only ones working longer hours as the holidays approach.

For several weeks, nine Kansas state employees have been voluntarily working weekends and late into the night to finish a review of a permit for a power plant.

Kansas Department of Health and Environment officials think they should be able to issue the air quality permit for the coal-fired plant of Sunflower Electric Power Corp. by the end of the year.

And that worries the coal plant’s opponents, who said the extra hours were a clear signal that the state was pushing the permit process too fast."

Karen Dillon reports for the Kansas City Star December 12, 2010. [2]

Air [3]
Climate Change [4]
Energy & Fuel [5]
Great Plains (IA KS ND NE MO SD) [6]
Public [7]
Source: Kansas City Star [2], 12/14/2010
  • Contact Us  |
  • Donate  |
  • Join  |
  • Members  |
  • Privacy & Security Policies  |
  • Reach SEJ Members  |
  • Renew  |
  • Site Map
The Society of Environmental Journalists
1629 K Street NW, Suite 300, Washington, DC 20006
Telephone: (202) 558-2055
Email: sej@sej.org
© 2026 The Society of Environmental Journalists. All Rights Reserved.
All graphics © SEJ, unless otherwise stated.

Source URL:https://www.sej.org/headlines/permit-process-coal-fired-plant-kansas-draws-criticism

Links
[1] https://www.sej.org/headlines/permit-process-coal-fired-plant-kansas-draws-criticism [2] http://www.kansascity.com/2010/12/12/2515548/permit-process-for-coal-fired.html [3] https://www.sej.org/category/topics-beat/air [4] https://www.sej.org/category/topics-beat/climate-change [5] https://www.sej.org/category/topics-beat/energy [6] https://www.sej.org/category/region/national/great-plains [7] https://www.sej.org/taxonomy/term/81