"Midwest Wind Energy Transmission Line Gets Supersized"

"The developer of a planned high-voltage transmission line from Kansas to Indiana yesterday announced that the project is being expanded in response to strong demand for wind energy from customers in the region.

Chicago-based Invenergy LLC, which purchased the Grain Belt Express project in 2018 and took over its development, plans to increase the line’s capacity 25 percent to 5,000 megawatts and boost its midpoint delivery capacity at a Missouri converter station fivefold to 2,500 MW.

Invenergy also announced it would build the $7 billion project in two phases, enabling the company to accelerate construction of the initial phase from Kansas to the Missouri converter station."

Jeffrey Tomich reports for E&E News July 12, 2022.

Source: E&E News, 07/13/2022